QUESTION

The µVision versions released earlier than v5.14.0.0, changing the target in the IDE did not force the complete project rebuild. However, in µVision v5.14 and later, if target changes, µVision always rebuilds the complete project even if no change has been introduced in the project. It seems that in the later versions of µVision, this condition has changed and now the project is completely rebuilt upon a target change. Why there is change in the behavior ?

ANSWER

When switching targets, µVision may detect that a module's "modified" status may have been lost and automatically forces a project rebuild.

MORE INFORMATION

Last Reviewed: Friday, February 24, 2017


Did this article provide the answer you needed?
 
Yes
No
Not Sure
 
  Arm logo
Important information

This site uses cookies to store information on your computer. By continuing to use our site, you consent to our cookies.

Change Settings

Privacy Policy Update

Arm’s Privacy Policy has been updated. By continuing to use our site, you consent to Arm’s Privacy Policy. Please review our Privacy Policy to learn more about our collection, use and transfers
of your data.